CAPM Practice: Determine how to follow and execute planned strategies or frameworks

Question 99 of 100 in Determine how to follow and execute planned strategies or frameworks

Pick an answer below — you'll get the explanation instantly, no signup.

Match each planned strategy or framework on the left with the appropriate execution response on the right. Items: 1. Communication management plan specifies monthly reports 2. Risk response plan identifies a contingency reserve 3. Quality management plan defines inspection checkpoints 4. Stakeholder engagement plan schedules quarterly reviews Which option correctly matches each item to its description?
Show answer & explanation

Correct answer: 1. Communication management plan specifies monthly reports → Distribute reports to stakeholders each month 2. Risk response plan identifies a contingency reserve → Access reserve funds when identified risks occur 3. Quality management plan defines inspection checkpoints → Conduct inspections at the defined intervals 4. Stakeholder engagement plan schedules quarterly reviews → Hold review meetings every three months

Explanation

Following planned strategies means executing the actions specified in each plan: distributing communications as scheduled, using reserves when risks materialize, conducting quality inspections at defined points, and engaging stakeholders according to the planned frequency. Each response demonstrates appropriate execution of the corresponding framework.

**Why not A:** This option incorrectly matches the communication plan with conducting inspections (which belongs to quality management), the risk response plan with holding quarterly reviews (which belongs to stakeholder engagement), the quality plan with distributing reports (which belongs to communications), and the stakeholder plan with accessing reserves (which belongs to risk management). Every pairing is incorrect.

**Why not B:** This option incorrectly matches the communication plan with accessing reserve funds (a risk response action) and the risk response plan with conducting inspections (a quality management action). The execution responses are scrambled across the wrong frameworks.

**Why not C:** This option incorrectly matches the communication plan with holding quarterly reviews (which belongs to stakeholder engagement) and the stakeholder plan with distributing reports (which belongs to communications). While the risk and quality pairings are correct, swapping communications and stakeholder engagement demonstrates confusion between information distribution and relationship management.

Key Concept

This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).