CAPM Practice: Determine how to follow and execute planned strategies or frameworks

Question 43 of 100 in Determine how to follow and execute planned strategies or frameworks

Pick an answer below — you'll get the explanation instantly, no signup.

Valentina Conteh is reviewing planned strategies at Terraform Urban. Match each project management area with the appropriate example of following its planned framework. Items: 1. Risk Management 2. Quality Management 3. Communications Management 4. Stakeholder Engagement Which option correctly matches each item to its description?
Show answer & explanation

Correct answer: 1. Risk Management → Updating the risk register when new threats are identified 2. Quality Management → Conducting inspections according to the quality metrics baseline 3. Communications Management → Distributing status reports as specified in the communications plan 4. Stakeholder Engagement → Engaging stakeholders based on the stakeholder engagement plan

Explanation

Following planned strategies means executing the documented approaches for each knowledge area: updating the risk register follows the risk management framework, conducting inspections per metrics follows the quality framework, distributing reports follows the communications framework, and engaging stakeholders per the plan follows the stakeholder management framework.

**Why not A:** This option assigns quality inspection to risk management, communications reporting to quality management, stakeholder engagement to communications management, and risk register updates to stakeholder engagement — all four matches are incorrect.

**Why not C:** This option assigns stakeholder engagement to risk management, which is incorrect. Risk management involves updating the risk register when new threats are identified, not engaging stakeholders. It also assigns risk register updates to stakeholder engagement; only the quality and communications matches are correct.

**Why not D:** This option assigns communications reporting to risk management, stakeholder engagement to quality management, risk register updates to communications management, and quality inspection to stakeholder engagement — every match is misaligned with the correct framework.

Key Concept

This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).

Share: