CAPM Practice: Determine how to follow and execute planned strategies or frameworks

Question 9 of 100 in Determine how to follow and execute planned strategies or frameworks

Pick an answer below — you'll get the explanation instantly, no signup.

Jabari Popovic is executing various planned strategies on his project at Gridstone AI. Match each project situation on the left with the appropriate response strategy or framework on the right. Items: 1. A key stakeholder requests information about project status and upcoming milestones 2. An identified risk event has occurred that impacts the project schedule 3. A team member is unclear about their assigned tasks for the current sprint 4. The customer wants to add a new feature that was not in the original scope Which option correctly matches each item to its description?
Show answer & explanation

Correct answer: 1. A key stakeholder requests information about project status and upcoming milestones → Follow the communication management plan to provide the appropriate status report 2. An identified risk event has occurred that impacts the project schedule → Implement the planned risk response and update relevant project documents 3. A team member is unclear about their assigned tasks for the current sprint → Refer to the work breakdown structure and iteration plan for task clarity 4. The customer wants to add a new feature that was not in the original scope → Review the scope management plan and follow the change control process

Explanation

Each situation requires following the appropriate planned strategy: stakeholder information requests are handled through the communication management plan; risk events trigger planned responses; task clarity comes from project planning documents; and scope changes follow the change control process. These examples demonstrate how to appropriately respond to various situations by executing planned frameworks.

**Why not A:** This option incorrectly matches stakeholder information requests to risk response, risk events to task clarity, task clarity to change control, and scope changes to communications. Each situation requires a different planned framework than what this option assigns.

**Why not B:** This option incorrectly matches stakeholder information requests to scope management and scope changes to communications. Stakeholder status requests should use the communication plan, and scope changes should follow the change control process.

**Why not C:** This option reverses nearly all matches. Stakeholder information requests are assigned to task clarity tools, risk events to scope management, task clarity to communications, and scope changes to risk response — none of which follow the correct planned frameworks.

Key Concept

This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).