CAPM Practice: Determine how to follow and execute planned strategies or frameworks
Question 41 of 100 in Determine how to follow and execute planned strategies or frameworks
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Continue weekly reports unless the change is formally approved through change control
Explanation
Changes to the communications management plan, even supervisor-suggested ones, should go through formal change control processes. Following the planned strategy means adhering to approved plans until changes are formally processed.
**Why not A:** Making the change immediately simply because the supervisor has authority bypasses the formal change control process. Even supervisor-requested changes to the communications management plan must follow the established procedures for evaluating and approving modifications.
**Why not B:** Reducing report frequency temporarily and monitoring feedback is an unauthorized change. This approach skips the formal change control process and introduces an unapproved modification that could impact stakeholder expectations and project governance.
**Why not D:** Surveying stakeholders is a reasonable activity but should not precede the change control process. The current plan specifies weekly reports, and any change — even one informed by stakeholder feedback — must go through formal approval before implementation.
Key Concept
This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).