Skip to content
CAPMHard

CAPM Practice: Determine how to document project controls of predictive, plan-based projects

A project manager is presenting to the board after project close. The project finished 12% over budget and 3 weeks late, but delivered all required scope and was accepted by the customer. The board asks 'Was this a successful project?' What is the BEST answer?

Key Concept

This question covers Determine how to document project controls of predictive, plan-based projects under Determine how to document project controls of predictive, plan-based projects (Predictive, Plan-Based Methodologies).

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free