Skip to content
CAPMHard

CAPM Practice: Determine how to document project controls of predictive, plan-based projects

A project is approaching completion and the sponsor wants an accurate forecast of total project cost. The project has CPI = 0.94, BAC = $800,000, EV = $720,000, AC = $766,000. What is the best EAC estimate and what does it tell the sponsor?

Key Concept

This question covers Determine how to document project controls of predictive, plan-based projects under Determine how to document project controls of predictive, plan-based projects (Predictive, Plan-Based Methodologies).

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free