CAPM Practice: Determine how to document project controls of predictive, plan-based projects

A project manager uses the '8/80 rule' when creating the project schedule. This rule states that:

Key Concept

This question covers Determine how to document project controls of predictive, plan-based projects under Determine how to document project controls of predictive, plan-based projects (Predictive, Plan-Based Methodologies).