Skip to content
CAPMEasy

CAPM Practice: Determine how to document project controls of predictive, plan-based projects

Question 72 of 84 in Determine how to document project controls of predictive, plan-based projects

Pick an answer below — you'll get the explanation instantly, no signup.

A project manager receives a defect report on a completed deliverable. After the defect is repaired, the deliverable must be:
Show answer & explanation

Correct answer: Re-inspected to confirm the defect was correctly repaired and no new defects were introduced

Explanation

After defect repair, the deliverable must undergo re-inspection to: (1) verify the original defect was correctly fixed; and (2) confirm that the repair did not introduce new defects. Quality control requires that repaired deliverables re-enter the inspection process. Only after successful re-inspection can the deliverable be formally accepted.

**Why not A:** Archiving the deliverable and not re-using it wastes the investment in creating it. A defect does not render a deliverable permanently unusable. Once properly repaired and verified through re-inspection, the deliverable should proceed through the normal acceptance process.

**Why not C:** Accepting the deliverable without further inspection after repair is risky. The repair itself could be incomplete or could have introduced new defects. Quality control requires verification that the repair was successful before formal acceptance.

**Why not D:** In PMBOK terms, a defect repair is itself a type of change request reviewed through Perform Integrated Change Control before the repair work is done. Once the repair has been made, however, the next step is not another change request—the repaired deliverable returns to quality control for re-inspection. Submitting it to the CCB at this point would not verify that the defect was fixed or that no new defects were introduced.

Key Concept

This question covers Determine how to document project controls of predictive, plan-based projects under Determine how to document project controls of predictive, plan-based projects (Predictive, Plan-Based Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free