CAPM Practice: Determine how to document project controls of predictive, plan-based projects
Question 51 of 85 in Determine how to document project controls of predictive, plan-based projects
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Cost Performance Index (CPI)
Explanation
CPI = EV/AC measures cost efficiency — the value earned per dollar spent. CPI directly answers 'Are we getting our money's worth?' An CPI > 1.0 means efficient (getting more than $1 of value per $1 spent); CPI < 1.0 means inefficient (spending more than the value earned). CPI is the primary metric for cost performance monitoring.
**Why not B:** Schedule Performance Index (SPI) measures schedule efficiency (EV/PV), not cost efficiency. SPI tells you how efficiently the project is using time relative to the plan, which is a separate dimension from cost performance.
**Why not C:** Budget at Completion (BAC) is the total approved budget for the project. It is a static planned value, not a performance metric. BAC does not measure efficiency — it represents the original cost target against which performance is compared.
**Why not D:** Schedule Variance (SV = EV - PV) measures schedule performance in dollar terms, not cost efficiency. SV indicates whether the project is ahead or behind schedule, which is distinct from whether cost spending is efficient.
Key Concept
This question covers Determine how to document project controls of predictive, plan-based projects under Determine how to document project controls of predictive, plan-based projects (Predictive, Plan-Based Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free