CAPM Practice: Determine how to document project controls of predictive, plan-based projects

Question 61 of 84 in Determine how to document project controls of predictive, plan-based projects

Pick an answer below — you'll get the explanation instantly, no signup.

In predictive project management, quality assurance (QA) differs from quality control (QC) in that QA:
Show answer & explanation

Correct answer: Audits project processes to ensure they are being followed, while QC inspects deliverables against quality standards

Explanation

Quality Assurance (QA) focuses on PROCESSES — auditing project processes to confirm they comply with defined standards and are likely to produce quality outcomes. Quality Control (QC) focuses on PRODUCTS — inspecting completed deliverables against quality standards to identify defects. QA is proactive (prevent defects through process compliance); QC is reactive (detect defects in completed work).

**Why not A:** QA is not the customer's responsibility. Quality assurance is performed by the project team (or a QA department) to ensure internal processes are being followed. Quality control inspection results may be reviewed by the customer during scope validation, but QA is an internal activity.

**Why not B:** This answer reverses the definitions. QA audits processes; QC inspects deliverables. Stating that QA inspects deliverables and QC monitors processes swaps the two concepts entirely.

**Why not C:** QA is not performed only at project completion. Quality assurance activities occur throughout execution to verify that processes are being followed continuously. Waiting until project end to audit processes would be too late to prevent quality issues.

Key Concept

This question covers Determine how to document project controls of predictive, plan-based projects under Determine how to document project controls of predictive, plan-based projects (Predictive, Plan-Based Methodologies).