Skip to content
CAPMHard

CAPM Practice: Determine how to document project controls of predictive, plan-based projects

Question 77 of 85 in Determine how to document project controls of predictive, plan-based projects

A project manager implements a formal change control process but encounters resistance from senior developers who argue it slows down innovation. What is the BEST response?
Show answer & explanation

Correct answer: Explain that change control protects the project from uncoordinated changes that could create cost overruns, schedule delays, and integration problems — while exploring ways to streamline the process for low-impact technical changes

Explanation

The right response balances governance and agility. Explain the value of change control (preventing uncoordinated changes that cascade into cost/schedule problems). Then find ways to make the process more efficient: maybe a streamlined track for minor technical changes with a small technical change board; faster turnaround times; clearer criteria for what requires full CCB review vs. a simplified process. Good governance doesn't have to be slow governance.

**Why not A:** Allowing senior developers to bypass change control creates a two-tier governance system that undermines the entire process. If some team members can bypass controls, others will question why they must follow them, and uncoordinated changes will erode project integrity.

**Why not B:** Eliminating change control entirely abandons a critical governance mechanism. Team morale concerns are important but should be addressed through process improvement, not by removing essential project controls that protect against uncoordinated changes.

**Why not C:** Escalating for disciplinary action is unnecessarily punitive and damages the collaborative relationship. The developers' concerns about process speed may be legitimate. The appropriate response is to explain the value of change control and work together to streamline it.

Key Concept

This question covers Determine how to document project controls of predictive, plan-based projects under Determine how to document project controls of predictive, plan-based projects (Predictive, Plan-Based Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free