CAPM Practice: Determine how to document project controls of predictive, plan-based projects
Question 52 of 84 in Determine how to document project controls of predictive, plan-based projects
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Update the risk register with the new probability assessment, review the existing response plan, and activate or enhance the risk response if warranted
Explanation
Risk monitoring requires ongoing reassessment of risk probability and impact as new information emerges. When a risk's probability increases significantly, the project manager should: update the risk register with the new assessment; review the existing response plan to determine if it is adequate; and if necessary, enhance or activate the response. Passive management of a now-high-probability risk is inadequate.
**Why not A:** Doing nothing because the risk is already in the register is inadequate. A significant change in probability from low to high fundamentally changes the risk profile and may render the existing response plan insufficient. Active reassessment and potential response enhancement are required.
**Why not C:** Closing the project based on a single risk probability increase is an extreme overreaction. The appropriate response is to reassess the risk, update the response plan if needed, and evaluate the business case impact. Project termination would only be considered if the overall project viability is fundamentally compromised.
**Why not D:** Creating a new project charter is unnecessary and inappropriate. The project charter authorizes the project and is created during initiation. Changed risk conditions are managed through risk monitoring and change control within the existing project framework, not by restarting authorization.
Key Concept
This question covers Determine how to document project controls of predictive, plan-based projects under Determine how to document project controls of predictive, plan-based projects (Predictive, Plan-Based Methodologies).