CAPM Practice: Determine how to document project controls of predictive, plan-based projects
Question 43 of 84 in Determine how to document project controls of predictive, plan-based projects
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Track, review, and regulate project progress and performance against the plan
Explanation
Monitoring and controlling involves measuring actual performance, comparing it to the plan, identifying variances, and taking corrective or preventive actions. It is an ongoing process that runs throughout project execution, providing the feedback loop that allows the project manager to maintain control over project outcomes.
**Why not A:** Developing the initial project plan and baselines is the purpose of the Planning process group. Planning occurs before execution begins and establishes the baselines that monitoring and controlling will later measure performance against.
**Why not B:** Formal acceptance of completed deliverables happens through Validate Scope, which is itself a Monitoring and Controlling process, and final acceptance is confirmed during project closing. However, obtaining acceptance is one specific activity within the process group, not its overall purpose. The purpose of monitoring and controlling is the broader tracking, review, and regulation of performance against the plan.
**Why not C:** Executing the work defined in the plan is the purpose of the Executing process group. Monitoring and controlling runs alongside execution to track whether the work being executed aligns with the plan, but the actual execution of work is a separate process group.
Key Concept
This question covers Determine how to document project controls of predictive, plan-based projects under Determine how to document project controls of predictive, plan-based projects (Predictive, Plan-Based Methodologies).