CAPM Practice: Determine how to document project controls of predictive, plan-based projects

Question 40 of 84 in Determine how to document project controls of predictive, plan-based projects

Pick an answer below — you'll get the explanation instantly, no signup.

Which of the following is a key output of the 'Control Quality' process?
Show answer & explanation

Correct answer: Verified deliverables (deliverables that have been inspected and meet quality standards)

Explanation

Control Quality inspects deliverables against quality standards and produces Verified Deliverables — products that have been checked and confirmed to meet quality requirements. Verified deliverables then feed into scope validation for formal customer acceptance. The quality management plan and quality metrics are planning outputs; test documents are inputs.

**Why not B:** Test and evaluation documents are inputs to the Control Quality process, not outputs. They provide the criteria and procedures used during inspections, but they are consumed by the process rather than produced by it.

**Why not C:** Quality metrics are outputs of the Plan Quality Management process. They define the measurements and acceptable ranges used during quality control but are created during planning, not during the Control Quality process itself.

**Why not D:** The quality management plan is an output of the Plan Quality Management process and serves as an input to Control Quality. It describes how quality will be managed but is created during planning, not as a result of performing quality control inspections.

Key Concept

This question covers Determine how to document project controls of predictive, plan-based projects under Determine how to document project controls of predictive, plan-based projects (Predictive, Plan-Based Methodologies).

Share: