CAPM Practice: Determine how to document project controls of predictive, plan-based projects
A project is experiencing significant scope creep. The project manager discovers that 15 new features were added by developers without change requests during the last 3 months. What is the MOST effective corrective approach?
Key Concept
This question covers Determine how to document project controls of predictive, plan-based projects under Determine how to document project controls of predictive, plan-based projects (Predictive, Plan-Based Methodologies).