CAPM Practice: Determine how to document project controls of predictive, plan-based projects
Question 82 of 84 in Determine how to document project controls of predictive, plan-based projects
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Final cost/schedule performance vs. baselines, summary of issues resolved, lessons learned highlights, and deliverable acceptance documentation
Explanation
A final project performance report comprehensively summarizes the project: final performance against scope/schedule/cost baselines (how did we do vs. plan?); how major issues were resolved; lessons learned; deliverable acceptance status. This document becomes part of organizational process assets and provides accountability for project outcomes.
**Why not A:** Financial data alone is far too narrow for an end-of-project performance report. A comprehensive report must also cover schedule performance, scope delivery, issues resolved, and lessons learned. Limiting the report to cost ignores the multidimensional nature of project success.
**Why not C:** Recommendations for the next project are only a small part of what belongs in a final report. The report's primary purpose is to document how this project performed against its baselines, what was delivered, and what was learned — not solely to advise future projects.
**Why not D:** The project charter and stakeholder register are initiating documents, not closing documents. A final performance report summarizes outcomes and results, not the inputs that launched the project. Including only these would provide no information about actual project performance.
Key Concept
This question covers Determine how to document project controls of predictive, plan-based projects under Determine how to document project controls of predictive, plan-based projects (Predictive, Plan-Based Methodologies).