CAPM Practice: Determine how to document project controls of predictive, plan-based projects
Question 46 of 85 in Determine how to document project controls of predictive, plan-based projects
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Link requirements to their origin and trace them through design, development, and testing
Explanation
The Requirements Traceability Matrix traces each requirement from its origin (stakeholder request or business need) through the project lifecycle — to design decisions, deliverables, and test cases. It ensures all requirements are implemented, tested, and accounted for, and provides a change impact analysis tool when requirements change.
**Why not A:** Documenting requirement priority for stakeholder communication is a useful function but is not the primary purpose of the RTM. The RTM's core value is ensuring traceability — linking each requirement through the full project lifecycle from origin to testing and delivery.
**Why not C:** Assigning team members to requirements is a resource management activity, not the purpose of a traceability matrix. The RTM tracks the lifecycle of requirements, not who is responsible for implementing them.
**Why not D:** Estimating the cost of implementing each requirement is a cost estimation activity. The RTM does not contain cost data — it traces requirements from their origin through design, development, and testing to ensure completeness and coverage.
Key Concept
This question covers Determine how to document project controls of predictive, plan-based projects under Determine how to document project controls of predictive, plan-based projects (Predictive, Plan-Based Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free