CAPM Practice: Determine how to document project controls for an adaptive project

Question 12 of 60 in Determine how to document project controls for an adaptive project

Pick an answer below — you'll get the explanation instantly, no signup.

The daily standup in adaptive projects is MOST important for:
Show answer & explanation

Correct answer: Team synchronization — identifying what was done, what will be done, and any impediments to coordination

Explanation

The daily standup is a team synchronization event — not a status report for management. The three classic questions (what did I do yesterday that helped the team's sprint goal? What will I do today? What impediments exist?) are about coordination among team members. The 15-minute format keeps it focused on synchronization, with deeper discussions taken offline.

**Why not A:** The daily standup is explicitly not a status report for management. Treating it as a reporting mechanism shifts the dynamic from peer coordination to upward accountability, which discourages candor and undermines team autonomy. The project manager or Scrum Master participates to facilitate and support — not to collect individual status updates.

**Why not B:** The product owner may attend standups but is not the target audience for individual progress reports. Backlog updates happen through backlog refinement, sprint planning, and sprint review — not during the daily standup. Framing the standup as a reporting event for the PO misrepresents its team-coordination purpose.

**Why not D:** Reviewing the burndown chart in detail and planning corrective actions is appropriate in a separate follow-up discussion after the standup — not during the 15-minute daily standup. Detailed analysis and corrective planning take longer than the standup format allows and should involve the full team's focused attention outside the brief synchronization window.

Key Concept

This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).