CAPM Practice: Determine how to document project controls for an adaptive project
Question 24 of 60 in Determine how to document project controls for an adaptive project
Show answer & explanation
Correct answer: Apply EVM concepts at the sprint level: PV = story points planned, EV = story points completed, AC = actual hours/costs — using story points as the unit of value
Explanation
EVM concepts can be adapted for agile projects. By treating story points as the 'value' unit: PV = story points planned for the sprint or release; EV = story points completed (meeting DoD); AC = actual hours or costs. This enables SPI and CPI calculations at sprint or release level, providing the cost performance visibility the PMO requires while using adaptive measurements. This 'Agile EVM' or 'Earned Business Value' approach satisfies organizational governance without abandoning adaptive practices.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free