CAPM Practice: Determine how to document project controls for an adaptive project

Question 26 of 60 in Determine how to document project controls for an adaptive project

Pick an answer below — you'll get the explanation instantly, no signup.

Which of the following best represents a project control artifact in an adaptive environment?
Show answer & explanation

Correct answer: A velocity chart tracking completed story points per iteration

Explanation

A velocity chart is a lightweight, team-driven control tool typical of agile environments. It tracks throughput over time and supports data-driven planning without requiring heavy administrative overhead.

**Why not A:** A detailed Gantt chart is a predictive artifact.

**Why not C:** Executive sign-off for every change is heavyweight predictive control.

**Why not D:** Monthly cost variance reports are predictive controls.

Key Concept

This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).