CAPMEasy
CAPM Practice: Determine how to document project controls for an adaptive project
Question 26 of 60 in Determine how to document project controls for an adaptive project
Which of the following best represents a project control artifact in an adaptive environment?
Show answer & explanation
Correct answer: A velocity chart tracking completed story points per iteration
Explanation
A velocity chart is a lightweight, team-driven control tool typical of agile environments. It tracks throughput over time and supports data-driven planning without requiring heavy administrative overhead.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free