CAPM Practice: Determine how to document project controls for an adaptive project
Question 46 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Conducting automated regression testing after every code change throughout development
Explanation
Continuous integration with automated testing is a core adaptive quality control practice. Running tests continuously catches defects immediately when they're cheapest to fix, rather than accumulating them for end-of-project testing.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free