Skip to content
CAPMMedium

CAPM Practice: Determine how to document project controls for an adaptive project

Question 46 of 60 in Determine how to document project controls for an adaptive project

Pick an answer below — you'll get the explanation instantly, no signup.

Which of the following is an example of a quality control practice in an adaptive project?
Show answer & explanation

Correct answer: Conducting automated regression testing after every code change throughout development

Explanation

Continuous integration with automated testing is a core adaptive quality control practice. Running tests continuously catches defects immediately when they're cheapest to fix, rather than accumulating them for end-of-project testing.

Key Concept

This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free