Skip to content
CAPMMedium

CAPM Practice: Determine how to document project controls for an adaptive project

Question 46 of 60 in Determine how to document project controls for an adaptive project

Pick an answer below — you'll get the explanation instantly, no signup.

Which of the following is an example of a quality control practice in an adaptive project?
Show answer & explanation

Correct answer: Conducting automated regression testing after every code change throughout development

Explanation

Continuous integration with automated testing is a core adaptive quality control practice. Running tests continuously catches defects immediately when they're cheapest to fix, rather than accumulating them for end-of-project testing.

**Why not A:** Quarterly audits are infrequent, process-focused quality assurance, not continuous quality control.

**Why not C:** Reviewing at the end of the project delays feedback until defects are most expensive to fix.

**Why not D:** Approval gates before testing add delay and discourage frequent testing.

Key Concept

This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free