CAPM Practice: Determine how to document project controls for an adaptive project
Question 19 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Risk register or risk backlog, maintained by the team and product owner
Explanation
Adaptive projects do identify and track risks, but they do so within adaptive conventions. Some teams maintain a risk register (same as predictive), while others use a 'risk backlog' integrated with the product backlog (risk items prioritized and addressed in sprints). The key is transparency about risks — how they're documented is less important than that they are visible and managed.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).