CAPM Practice: Determine how to document project controls for an adaptive project
Question 5 of 60 in Determine how to document project controls for an adaptive project
Show answer & explanation
Correct answer: It enables forecasting of how much work can be delivered in future sprints and when the project will complete
Explanation
Velocity tracking (measuring story points completed per sprint over multiple sprints) provides empirical data for forecasting: how many sprints will it take to complete the remaining backlog? When will a specific release be ready? These forecasts are based on actual team performance rather than estimates, making them increasingly reliable as velocity stabilizes.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).