CAPM Practice: Determine how to document project controls for an adaptive project
Question 60 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Transparency makes project status, progress, and process visible to all — enabling timely inspection and adaptation, which are the foundation of empirical control in Scrum
Explanation
Scrum's empirical model (transparency → inspection → adaptation) makes transparency foundational to all controls. Without visibility into what's really happening, inspection is impossible and adaptation is uninformed. Artifacts like the sprint backlog, burndown chart, and task board all support transparency-based control.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).