CAPM Practice: Determine how to conduct stakeholder communication
Question 30 of 67 in Determine how to conduct stakeholder communication
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Segment stakeholders by role, interest, and influence, then design tailored communication approaches for each segment
Explanation
With many diverse stakeholders, segmentation is essential. Group stakeholders by characteristics (executives, end users, IT, regulatory) and design targeted communication for each group — appropriate detail, format, and frequency — rather than a one-size-fits-all approach.
**Why not B:** Sending all 40 stakeholders identical weekly emails ignores the diverse information needs across different roles. Executives need strategic summaries, end users need operational details, and IT staff need technical specifications. A one-size-fits-all approach overwhelms some while under-serving others.
**Why not C:** Assigning one team member to communicate with each stakeholder individually is impractical and resource-prohibitive for 40 stakeholders. This approach would require an enormous communication effort and does not leverage the efficiency of group communication for stakeholders with similar information needs.
**Why not D:** Holding one large weekly meeting for all 40 stakeholders simultaneously would be unproductive. Large meetings make it difficult for individuals to contribute meaningfully, and the diverse information needs across stakeholder groups mean much of the content would be irrelevant to most attendees.
Key Concept
This question covers Determine how to conduct stakeholder communication under Determine how to conduct stakeholder communication (Business Analysis Frameworks).