CAPM Practice: Determine how to conduct stakeholder communication
Question 16 of 67 in Determine how to conduct stakeholder communication
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A structured review where the BA presents requirements to stakeholders and subject matter experts to gather feedback and identify issues
Explanation
A requirements walkthrough is a review technique where the BA presents requirements documentation to stakeholders for validation. The goal is to identify errors, ambiguities, and missing requirements through collaborative review.
**Why not A:** Taking stakeholders on a physical tour of a project facility is a site visit, not a requirements walkthrough. A requirements walkthrough is a structured review session where the BA presents requirements documentation for feedback, conducted in a meeting setting rather than a physical location tour.
**Why not B:** A presentation of completed software for final approval describes a demo or acceptance review, not a requirements walkthrough. Requirements walkthroughs occur during the requirements phase to review documentation before development, not after software is complete.
**Why not D:** Walking new team members through documentation describes an onboarding or knowledge transfer activity. A requirements walkthrough is specifically a validation technique where the BA presents requirements to stakeholders and subject matter experts to identify errors, gaps, and ambiguities.
Key Concept
This question covers Determine how to conduct stakeholder communication under Determine how to conduct stakeholder communication (Business Analysis Frameworks).