CAPM Practice: Determine how to conduct stakeholder communication
Question 67 of 67 in Determine how to conduct stakeholder communication
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Informing provides one-way communication of status and decisions; involving actively engages stakeholders in contributing to analysis, decisions, or validation — building ownership and producing better requirements
Explanation
The distinction is critical. Informing stakeholders about requirements decisions builds awareness but not ownership. Involving them in creating requirements builds deep understanding, surfaces valuable insights, and creates the buy-in needed for adoption and change management.
**Why not A:** Segmenting communication strategy purely by stakeholder type (business vs. technical) rather than by what the project needs from each stakeholder is an oversimplification. Technical stakeholders often need to be deeply involved in requirements discovery to surface feasibility constraints and design implications.
**Why not B:** Stakeholder involvement, when managed well, improves requirements quality and stakeholder buy-in rather than causing scope creep. Scope creep typically results from poor change control, not from involving stakeholders in structured requirements processes.
**Why not D:** Treating informing and involving as synonymous collapses an important strategic distinction. Informing is one-directional (sending information), while involving is bi-directional (soliciting contribution). The choice between them directly affects requirements quality and stakeholder commitment to outcomes.
Key Concept
This question covers Determine how to conduct stakeholder communication under Determine how to conduct stakeholder communication (Business Analysis Frameworks).