CAPM Practice: Determine how project methodologies influence business analysis processes

Question 15 of 67 in Determine how project methodologies influence business analysis processes

Pick an answer below — you'll get the explanation instantly, no signup.

A project uses SAFe (Scaled Agile Framework) with multiple teams. How does this affect BA work?
Show answer & explanation

Correct answer: SAFe requires BAs to work at multiple levels: portfolio (epics and value streams), program (features and Program Increment planning), and team (user stories and acceptance criteria)

Explanation

SAFe introduces structured planning at multiple levels. BAs may work at: portfolio level (analyzing epics, business outcomes), program level (decomposing features, PI planning support), and team level (story refinement, acceptance criteria). Requirements hierarchy matches the planning hierarchy.

**Why not A:** SAFe involves multiple teams with different needs, so one BA cannot serve all teams identically. BAs must adapt their work to the appropriate level — portfolio epics require different analysis than team-level user stories — and may specialize at different levels of the framework.

**Why not C:** SAFe is an agile scaling framework, not a waterfall approach. It uses agile practices like user stories, acceptance criteria, and iterative delivery at the team level, while adding structured planning ceremonies like PI Planning at the program level.

**Why not D:** SAFe does not eliminate the need for BA work. While teams are self-organizing in their execution, the complexity of multi-team coordination, feature decomposition, and cross-team dependency management actually increases the need for BA skills at portfolio, program, and team levels.

Key Concept

This question covers Determine how project methodologies influence business analysis processes under Determine how project methodologies influence business analysis processes (Business Analysis Frameworks).