CAPM Practice: Determine how project methodologies influence business analysis processes

Question 2 of 67 in Determine how project methodologies influence business analysis processes

Pick an answer below — you'll get the explanation instantly, no signup.

In a predictive (waterfall) project, what is the primary BA responsibility during the initiation/planning phase?
Show answer & explanation

Correct answer: Completing comprehensive requirements documentation that will serve as the basis for all downstream design and development

Explanation

In predictive projects, the BA front-loads work — comprehensive requirements documents (BRD, functional specs) are produced before design begins, because changes after design are expensive and because the entire project plan depends on stable requirements.

**Why not A:** Daily standups and product backlog management are Scrum/agile practices. In a predictive (waterfall) project, there are no sprints or backlogs. The BA's focus during initiation/planning is on comprehensive upfront requirements documentation.

**Why not B:** Sprint retrospectives are an agile practice that does not exist in predictive project methodologies. Waterfall projects follow sequential phases, and the planning phase centers on thorough requirements elicitation and documentation.

**Why not D:** User stories and iterations are agile artifacts and practices. In a predictive project, the BA produces detailed requirements specifications and use cases during planning, not user stories organized into iterations.

Key Concept

This question covers Determine how project methodologies influence business analysis processes under Determine how project methodologies influence business analysis processes (Business Analysis Frameworks).