CAPM Practice: Demonstrate an understanding of the various project life cycles and processes
Question 6 of 94 in Demonstrate an understanding of the various project life cycles and processes
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Projects create unique deliverables while operations sustain the business through repetitive activities
Explanation
Projects are temporary endeavors undertaken to create a unique product, service, or result. Operations are ongoing activities that sustain the business and are repetitive in nature. Yasmin's project (developing the portal) is temporary and creates something unique, while the subsequent maintenance by IT operations is ongoing and repetitive.
**Why not B:** This reverses the definitions. Projects are temporary and unique, while operations are ongoing and repetitive — not the other way around. Yasmin's portal development is the temporary project, and the IT team's ongoing maintenance is the operational work.
**Why not C:** Both projects and operations require management. Operations are managed by functional managers or operations managers. The distinction is not about whether management is required but about the nature of the work — temporary and unique versus ongoing and repetitive.
**Why not D:** The use of predictive or adaptive approaches is not a distinguishing factor between projects and operations. Projects can use either approach depending on their characteristics, and operations can also adopt various management methodologies.
Key Concept
This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).