Question 57 of 94 in Demonstrate an understanding of the various project life cycles and processes

Pick an answer below — you'll get the explanation instantly, no signup.

Mila Hwang works at Warden Defense where she manages multiple related projects that share resources and contribute to strategic business objectives. What is Mila managing?
Show answer & explanation

Correct answer: A program of coordinated projects

Explanation

A program is a group of related projects managed in a coordinated manner to obtain benefits not available from managing them individually. The key indicators are 'related projects' and 'share resources' working toward common strategic objectives.

**Why not A:** Operational work is ongoing and repetitive, without the coordinated structure of related projects. Mila's work involves managing multiple related projects together, which goes beyond simple operational work with project components.

**Why not B:** A portfolio is a collection of projects, programs, and operational work managed as a group to achieve strategic objectives. While portfolios contain projects, the key distinction is that Mila's projects are related and share resources, indicating coordinated management for combined benefits, which defines a program.

**Why not C:** A project with multiple phases is still a single project divided into sequential stages. Mila is managing multiple separate but related projects that share resources and contribute to common strategic objectives, which is the definition of a program.

Key Concept

This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).