Question 55 of 94 in Demonstrate an understanding of the various project life cycles and processes

Pick an answer below — you'll get the explanation instantly, no signup.

Match each project management concept on the left with its correct description on the right. Items: 1. Project 2. Program 3. Portfolio 4. Operations Which option correctly matches each item to its description?
Show answer & explanation

Correct answer: 1. Project → Temporary endeavor to create a unique deliverable 2. Program → Related projects managed together for benefits 3. Portfolio → Collection managed to achieve strategic objectives 4. Operations → Ongoing work that sustains the organization

Explanation

A project is temporary and creates something unique. A program groups related projects for coordinated benefits. A portfolio contains projects, programs, and operations aligned to strategy. Operations are ongoing activities that sustain business functions.

**Why not B:** This option assigns collection management to project and ongoing work to program, and misassigns portfolio and operations as well. A project is a temporary endeavor, not a collection of efforts. A program coordinates related projects, not sustains ongoing work. A portfolio is not a temporary endeavor, and operations are not related projects managed together.

**Why not C:** This option misassigns program characteristics to project and portfolio characteristics to program. A project is temporary with a unique deliverable, not a group of related projects. A portfolio is managed for strategic objectives, not sustains operations.

**Why not D:** This option swaps the definitions of project and operations. A project is not ongoing work, and operations are not a temporary endeavor to create a unique deliverable. Only the program and portfolio definitions are matched correctly.

Key Concept

This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).