CAPM Practice: Demonstrate an understanding of the various project life cycles and processes
Question 59 of 94 in Demonstrate an understanding of the various project life cycles and processes
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: 1. Risk → An uncertain event that, if it occurs, could affect the project 2. Issue → A current problem requiring immediate action 3. Assumption → A factor considered to be true without proof or demonstration 4. Constraint → A limiting factor that restricts project options
Explanation
Risks are uncertain future events requiring proactive planning. Issues are current problems requiring reactive resolution. Assumptions are beliefs held as true that need validation. Constraints are limiting factors (budget, time, resources, regulations) that bound the project.
**Why not A:** This option incorrectly assigns the assumption definition to risk and the constraint definition to issue. Risks are uncertain events, not accepted-as-true factors. Issues are current problems, not limiting factors.
**Why not C:** This option incorrectly assigns the constraint definition to risk and the risk definition to constraint. Risks are limiting factors in this option, which is wrong. Constraints limit options, while risks are uncertain future events.
**Why not D:** This option assigns every item the wrong definition. Risks are not current problems, issues are not accepted-as-true factors, assumptions are not limiting factors, and constraints are not uncertain events.
Key Concept
This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).