CAPM Practice: Demonstrate an understanding of the various project life cycles and processes
Question 17 of 94 in Demonstrate an understanding of the various project life cycles and processes
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A risk, because it is an uncertain event that could negatively impact the project schedule.
Explanation
This is a risk because it is an uncertain future event (might not be available) that could have a negative impact on the project. Risks are potential problems that have not yet occurred but could affect objectives.
**Why not B:** A constraint is a fixed limitation already imposed on the project, such as a hard deadline or regulatory requirement. The server availability is uncertain ("might not be available"), making it a potential future event rather than a known limitation.
**Why not C:** An issue is a current problem that is already affecting the project. The database server unavailability has not yet occurred; it is a potential future event. Since the testing is two weeks away, this is still in the realm of uncertainty, not a current problem.
**Why not D:** An assumption would mean the team is accepting something as true for planning purposes. The team is not assuming the server will be unavailable; rather, they are flagging uncertainty about its availability, which is the definition of a risk.
Key Concept
This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).