CAPM Practice: Demonstrate an understanding of the various project life cycles and processes
Question 67 of 94 in Demonstrate an understanding of the various project life cycles and processes
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Changing requirements are an assumption, fixed timeline is a constraint, vendor uncertainty is a risk, and competitor launch is an issue
Explanation
An assumption is something believed to be true without proof (the plan expects requirements to change). A constraint is a limiting factor (fixed 18-month timeline). A risk is an uncertain event that could impact the project (vendor may not deliver on time). An issue is a current problem requiring action (competitor has already launched). Fatou correctly identifies: changing requirements as an assumption about future behavior, the fixed timeline as a constraint limiting flexibility, vendor uncertainty as a risk that may or may not occur, and the competitor launch as an issue that exists now.
**Why not A:** This option incorrectly classifies changing requirements as a risk rather than an assumption. The team's plan already treats changing requirements as expected, based on the nature of clinical trials — this is something accepted as true for planning (an assumption), not an uncertain event. It also incorrectly classifies vendor uncertainty as an assumption when it is an uncertain event that may or may not occur — a risk.
**Why not C:** This option incorrectly classifies changing requirements as a constraint and the fixed timeline as a risk. The fixed timeline is an imposed limitation (a constraint), not an uncertain event. Changing requirements reflect an expectation about future behavior (an assumption), not a restriction on project options.
**Why not D:** This option incorrectly classifies changing requirements as an issue, the fixed timeline as an assumption, and vendor uncertainty as a constraint. Changing requirements have not yet materialized as a current problem. The fixed timeline is imposed, not assumed. Vendor uncertainty is a future possibility (a risk), not a limitation on project options.
Key Concept
This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).