CAPM Practice: Demonstrate an understanding of the various project life cycles and processes

Question 38 of 94 in Demonstrate an understanding of the various project life cycles and processes

Pick an answer below — you'll get the explanation instantly, no signup.

Halima Calloway is reviewing how projects serve as vehicles for organizational change at Kilowatt Power. Match each project outcome on the left with the type of change it enables on the right. Items: 1. Redesigning end-to-end business workflows around a new enterprise resource planning system 2. Launching a new product line in a different market 3. Restructuring the organization into cross-functional teams 4. Adopting cloud-based collaboration tools across the company Which option correctly matches each item to its description?
Show answer & explanation

Correct answer: 1. Redesigning end-to-end business workflows around a new enterprise resource planning system → Process change - transforming how work is performed 2. Launching a new product line in a different market → Strategic change - entering new business areas 3. Restructuring the organization into cross-functional teams → Structural change - modifying organizational design 4. Adopting cloud-based collaboration tools across the company → Technological change - adopting new systems and tools

Explanation

Projects are vehicles for change in organizations. An ERP-driven redesign of business workflows transforms how work is performed (process change); launching a new product line represents strategic expansion; restructuring changes organizational design; and adopting new collaboration tools represents technological advancement. Each project type enables a specific category of organizational change.

**Why not A:** All four pairings in this option are wrong. It classifies the ERP workflow redesign as structural change (it is process change), the new product line as technological change (it is strategic change), restructuring into cross-functional teams as process change (it is structural change), and cloud tool adoption as strategic change (it is technological change).

**Why not B:** This option incorrectly classifies the ERP workflow redesign as strategic change and launching a new product line as structural change. Entering a new market is a strategic move, not a structural one, and redesigning workflows transforms business processes, not the organization's strategic direction. Multiple pairings are wrong.

**Why not C:** This option classifies the ERP workflow redesign as technological change; the item describes transforming how work is performed, which is process change. It also classifies cloud tool adoption as process change, when adopting new tools is technological change.

Key Concept

This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).