What is the PRIMARY difference between predictive and adaptive project approaches?
Show answer & explanation

Correct answer: Predictive approaches define detailed scope, schedule, and cost upfront, while adaptive approaches develop these progressively throughout the project

Explanation

The key distinction is when and how requirements and plans are developed. Predictive approaches plan extensively upfront with detailed requirements, while adaptive approaches embrace change and develop requirements iteratively throughout the project lifecycle.

**Why not B:** Both predictive and adaptive approaches involve stakeholders. Predictive approaches engage stakeholders through formal reviews and approvals, while adaptive approaches involve them more continuously. The distinction is about how requirements and plans are developed, not stakeholder involvement levels.

**Why not C:** Neither approach is inherently more cost-effective. The cost-effectiveness depends on the project context, requirements stability, and organizational factors. Predictive approaches can be very efficient for well-understood work, while adaptive approaches reduce waste when requirements are uncertain.

**Why not D:** Both approaches can be used across industries. Predictive approaches are common in construction but also used in software. Adaptive approaches originated in software but are applied to manufacturing, marketing, and other fields. The distinction is about planning methodology, not industry applicability.

Key Concept

This question covers Demonstrate an understanding of the various project life cycles and processes under Demonstrate an understanding of the various project life cycles and processes (Project Management Fundamentals and Core Concepts).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free