CAPM Practice: Demonstrate an understanding of project roles and responsibilities

Question 62 of 94 in Demonstrate an understanding of project roles and responsibilities

Pick an answer below — you'll get the explanation instantly, no signup.

Arun Pemberton, a project manager at Vector Aerospace, notices that his sponsor keeps making technical decisions that should be made by the project team. What should Arun do?
Show answer & explanation

Correct answer: Discuss role boundaries with the sponsor and clarify that the team should make technical decisions within their domain.

Explanation

The project manager should clarify roles and responsibilities through professional discussion. The sponsor provides strategic direction and resources, while the project team possesses technical expertise for implementation decisions. Open communication resolves this role confusion.

**Why not A:** Escalating to the sponsor's manager is an aggressive approach that could damage the working relationship. Role boundary issues should first be addressed through direct, professional conversation between the project manager and the sponsor.

**Why not C:** Implementing the sponsor's technical decisions without question undermines the project team's expertise and could lead to suboptimal technical outcomes. The team should make decisions within their domain of expertise.

**Why not D:** Accepting all sponsor decisions based on organizational authority ignores the separation of strategic and technical responsibilities. The sponsor provides direction and resources, but technical decisions should be made by those with the relevant expertise.

Key Concept

This question covers Demonstrate an understanding of project roles and responsibilities under Demonstrate an understanding of project roles and responsibilities (Project Management Fundamentals and Core Concepts).