CAPM Practice: Demonstrate an understanding of project roles and responsibilities
Question 81 of 94 in Demonstrate an understanding of project roles and responsibilities
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Coach
Explanation
Zuri is acting as a coach by helping the team member develop their skills and confidence to present ideas effectively. Coaching involves developing team members' capabilities and supporting their growth.
**Why not A:** An initiator proposes new projects or ideas. Zuri is not starting a new initiative — she is helping an existing team member develop their presentation skills and addressing their frustration, which is a coaching activity focused on individual growth.
**Why not B:** A negotiator works to reach agreements between parties with competing interests. Zuri is not negotiating terms or resolving competing demands — she is providing one-on-one developmental support to help a team member improve their ability to contribute effectively in meetings.
**Why not C:** A working member performs the actual technical work on the project. Zuri is not doing technical project work; she is investing time in developing a team member's skills and confidence, which is a coaching and mentoring activity.
Key Concept
This question covers Demonstrate an understanding of project roles and responsibilities under Demonstrate an understanding of project roles and responsibilities (Project Management Fundamentals and Core Concepts).