CAPM Practice: Demonstrate an understanding of project management planning
Question 90 of 100 in Demonstrate an understanding of project management planning
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A milestone indicating a significant point in the project
Explanation
A milestone represents a significant point or event in the project with zero duration. 'FDA Approval Received' marks an important achievement but does not consume time itself. Milestones are used to track progress and signal completion of major deliverables or phases.
**Why not A:** A baseline measurement is a reference point for performance tracking, such as a schedule or cost baseline. "FDA Approval Received" is not a baseline — it is a specific event marker in the project timeline that signifies an important achievement.
**Why not B:** A resource allocation describes the assignment of people, equipment, or budget to project activities. "FDA Approval Received" does not represent a resource assignment — it marks the occurrence of a significant regulatory event.
**Why not C:** A task with a three-week duration estimate represents an activity that requires time and resources to complete. "FDA Approval Received" is a point in time with zero duration — it marks when approval was obtained, not an activity that takes three weeks to perform.
Key Concept
This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).