CAPM Practice: Demonstrate an understanding of project management planning

Question 54 of 100 in Demonstrate an understanding of project management planning

Pick an answer below — you'll get the explanation instantly, no signup.

Vikram Blackwood is leading a software upgrade project at Wavelength Biotech. During planning, he needs to identify all resources required. What should he consider when determining the number and type of resources?
Show answer & explanation

Correct answer: Human resources, equipment, materials, and any other assets needed to complete project work

Explanation

Resource determination involves identifying all types of resources needed for the project, including human resources (team members, specialists), physical resources (equipment, materials, facilities), and other assets. This comprehensive approach ensures all resource requirements are planned for appropriately.

**Why not B:** Limiting resource consideration to only full-time employees with technical skills ignores other essential resource types such as part-time staff, contractors, physical equipment, materials, and facilities. A comprehensive resource plan must account for all types of resources.

**Why not C:** Restricting resources to those currently available within the organization may result in gaps in capability or capacity. Resource planning should identify all needed resources first, then determine how to acquire them, whether internally or through procurement.

**Why not D:** Assuming resource needs are the same as a previous project ignores the unique characteristics of each project. Different scope, technology, timelines, and constraints mean that resource requirements must be determined based on the current project's specific needs.

Key Concept

This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).