CAPM Practice: Demonstrate an understanding of project management planning
Question 4 of 100 in Demonstrate an understanding of project management planning
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Work with the team to develop and document an appropriate risk response strategy
Explanation
High probability and high impact risks require proactive response strategies. The project manager should work with the team to develop appropriate responses (avoid, mitigate, transfer, or accept) and document them in the risk register.
**Why not A:** Waiting until the risk occurs before taking action is reactive risk management. A high-probability, high-impact risk without a response strategy is a significant exposure that requires proactive planning to mitigate potential damage.
**Why not B:** Transferring the risk to the sponsor is not the same as developing a response strategy. The sponsor is not the appropriate risk owner for all risks, and the team should develop an appropriate response (avoid, mitigate, transfer, or accept) based on the risk's characteristics.
**Why not C:** Removing an unaddressed risk from the register would hide a significant project threat. The absence of a response strategy is a gap that needs to be filled, not a reason to remove the risk from documentation and monitoring.
Key Concept
This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free