CAPM Practice: Demonstrate an understanding of project management planning
Question 96 of 100 in Demonstrate an understanding of project management planning
Pick an answer below — you'll get the explanation instantly, no signup. A free account saves your progress.
Show answer & explanation
Correct answer: The skills required for each task, the duration of work, and the availability of qualified resources
Explanation
Resource planning requires analyzing the skills needed for each work package, estimating how long each type of work will take, and assessing the availability of resources with the required skills. This comprehensive approach ensures the right resources are planned for the right work.
**Why not A:** The total number of people in the organization is irrelevant if they lack the required skills or availability. Resource planning must focus on matching specific skill requirements to qualified, available resources, not simply counting potential headcount.
**Why not B:** Budget is an important factor but not the only consideration. Resource planning must also account for skills, availability, and task duration. Planning solely around budget ignores whether the right expertise is available and whether timelines are realistic.
**Why not D:** Team member preferences may be considered for morale and engagement, but they are not the primary factor in resource planning. The primary drivers are matching required skills to tasks, estimating work duration, and confirming resource availability.
Key Concept
This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).