CAPM Practice: Demonstrate an understanding of project management planning
Question 74 of 100 in Demonstrate an understanding of project management planning
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Review the organizational resource calendar and consult with functional managers about availability
Explanation
Before making any decisions about acquiring resources or adjusting plans, Zuri should first determine what resources are actually available. Reviewing the resource calendar and consulting with functional managers provides the information needed to assess availability and plan accordingly.
**Why not A:** Reducing project scope before even checking resource availability is premature. Zuri should first determine what resources are available before making scope decisions. Scope changes should only be considered after understanding the actual resource situation.
**Why not B:** Creating a staffing management plan is an important planning activity, but it documents resource requirements — it does not determine availability. Zuri first needs to check what resources are actually available by consulting calendars and functional managers before documenting the plan.
**Why not D:** Submitting a purchase order for contract resources assumes internal resources are unavailable before checking. External contracting should only be considered after confirming that existing organizational resources cannot meet the need, making it premature as a first step.
Key Concept
This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free