CAPM Practice: Demonstrate an understanding of project management planning
Question 88 of 100 in Demonstrate an understanding of project management planning
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Conduct knowledge transfer sessions with the operations team, provide operational documentation, and obtain formal acceptance of the deliverables.
Explanation
Successful project closure and transition requires active knowledge transfer to those who will operate or maintain the deliverable. This includes conducting training/knowledge transfer sessions, providing relevant documentation, and obtaining formal acceptance. This ensures the operations team can successfully take ownership.
**Why not B:** While celebrating team success is positive for morale, it does not address the operational needs of the transition. Tendai needs knowledge transfer, documentation, and formal acceptance to successfully take ownership of the system.
**Why not C:** Simply archiving documents and notifying Tendai of their availability is insufficient for successful transition. Active knowledge transfer, operational documentation, and formal acceptance are needed to ensure the operations team can effectively maintain and support the system.
**Why not D:** Releasing resources immediately without proper knowledge transfer would leave the operations team without the support needed to understand and maintain the system. Successful transition requires structured handover activities before project resources are released.
Key Concept
This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).