CAPM Practice: Demonstrate an understanding of project management planning
Question 60 of 100 in Demonstrate an understanding of project management planning
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A milestone represents a significant point or event in the project with zero duration, while a task duration measures the time required to complete an activity
Explanation
A milestone marks a significant point or achievement in the project timeline and has zero duration—it's a moment in time. Task duration measures the length of time needed to complete a specific activity and consumes time on the schedule.
**Why not A:** Milestones and task durations are used in both agile and predictive projects. The distinction is not about project methodology but about the nature of the schedule element: milestones are zero-duration reference points, while task durations represent the time to complete work.
**Why not C:** Milestones can occur at any significant point in the project, not only at the end of phases. "Foundation Complete" marks the completion of a specific deliverable, which is not necessarily a phase boundary. Task durations apply to all activities throughout the project.
**Why not D:** Milestones do not require resources or budget allocation — they have zero duration and represent a point in time. Tasks are the schedule elements that consume resources and budget to complete their defined work activities.
Key Concept
This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).