CAPM Practice: Demonstrate an understanding of project management planning
Question 37 of 100 in Demonstrate an understanding of project management planning
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A milestone represents a significant point with zero duration, while a task duration represents the time needed to complete work
Explanation
A milestone marks a significant point or event in the project schedule and has zero duration—it is a moment in time. A task duration represents the length of time required to complete a specific work activity and consumes time on the schedule.
**Why not A:** Both milestones and task durations can appear on a Gantt chart. A Gantt chart displays the full project schedule including activities with durations and milestones as diamond markers. The distinction is about duration, not where they appear.
**Why not C:** This reverses the relationship. Milestones have zero duration and do not require resources to complete — they are simply significant points in time. Tasks require resources and effort to complete their defined work.
**Why not D:** Milestones and task durations are used in both agile and predictive projects. The distinction between them is about duration (zero vs. defined), not about which project approach they belong to.
Key Concept
This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).