CAPM Practice: Demonstrate an understanding of project management planning
Question 32 of 100 in Demonstrate an understanding of project management planning
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Milestones represent significant points or events with zero duration while tasks have a defined duration
Explanation
Milestones are significant points or events in the project schedule that have zero duration—they mark the completion of major deliverables, phase transitions, or key decision points. Tasks (or activities) are work efforts that consume time and have a defined duration.
**Why not A:** Milestones do not consume resources — they are zero-duration points in the schedule. Tasks are the schedule elements that require resource allocation to complete the associated work effort.
**Why not C:** Milestones do not inherently require stakeholder approval, and tasks are not always completed independently. The distinction is about duration: milestones have zero duration as significant reference points, while tasks have defined durations representing actual work.
**Why not D:** Milestones can occur at any significant point in the project, not only at phase endings. They can mark key decision points, deliverable completions, or external events. Similarly, tasks occur throughout phases and are not limited to within-phase activities.
Key Concept
This question covers Demonstrate an understanding of project management planning under Demonstrate an understanding of project management planning (Project Management Fundamentals and Core Concepts).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free