CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques
Question 52 of 105 in Demonstrate an understanding of common problem-solving tools and techniques
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Nominal Group Technique
Explanation
The Nominal Group Technique involves individual silent idea generation, group sharing, discussion, and then voting or ranking to prioritize options. It structures group decision-making to ensure fair participation and reduce the influence of dominant personalities.
**Why not A:** Brainstorming is designed for open, free-flowing idea generation without judgment. The scenario describes a structured process where members independently rank existing solutions, which is characteristic of the Nominal Group Technique, not the unstructured ideation of brainstorming.
**Why not B:** Force field analysis identifies driving and restraining forces for or against a proposed change. It does not involve independent ranking of multiple solutions by participants. The technique described uses individual ranking and aggregation, which is specific to the Nominal Group Technique.
**Why not D:** The Delphi Technique involves multiple rounds of anonymous expert input, typically conducted through questionnaires with feedback between rounds to reach consensus. The scenario describes a single round of independent ranking in a group setting, which matches the Nominal Group Technique, not the iterative anonymous process of the Delphi method.
Key Concept
This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).