CAPM Practice: Demonstrate an understanding of common problem-solving tools and techniques
Question 45 of 105 in Demonstrate an understanding of common problem-solving tools and techniques
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Explore the relationship or correlation between two variables
Explanation
A scatter diagram plots pairs of numerical data on X and Y axes to visually explore whether a relationship exists between two variables. A positive or negative correlation pattern in the data suggests a relationship that can be investigated further.
**Why not A:** Determining if a process is within statistical control limits is the purpose of a control chart, which plots data over time with upper and lower control limits. Scatter diagrams explore relationships between two variables but do not include control limits.
**Why not B:** Prioritizing defects by frequency of occurrence is the purpose of a Pareto chart, which ranks categories to identify the most significant contributors. Scatter diagrams show the relationship between two variables, not the ranking of individual categories.
**Why not C:** Showing the distribution of defects across project phases could be done with a histogram or bar chart. Scatter diagrams plot paired data points to reveal correlations, not to display distribution across categories or phases.
Key Concept
This question covers Demonstrate an understanding of common problem-solving tools and techniques under Demonstrate an understanding of common problem-solving tools and techniques (Project Management Fundamentals and Core Concepts).